RAILCAMP Home

The Howard Street Tunnel - Moving the Freight Through Baltimore

reprinted by permission from The National Railway Bulletin, Volume 66, Number 5, 2001.

Page 1 of 1


    The Howard Street Tunnel- Moving the Freight Through Baltimore

    Jeffrey Smith


    In the late 1800s, the Baltimore & Ohio Railroad was faced with a difficult problem. Until 1885, the B&O leased track through Baltimore to connect its eastern and western routes. In 1884, B&O rival The Pennsylvania Railroad, purchased the track the B&O had been leasing leaving the B&O with no way to get trains through Baltimore. The city of Baltimore was unwilling to allow a new railroad line to be built through the middle of the city and the B&O could not have afforded the land acquisitions required to build such a line. To further complicate matters, hills on the Western side of Baltimore were too steep to build track around. This forced the B&O to construct the Belt Line, a 7.3 mile route along the eastern side of Baltimore. The project included the construction of the 1.4 mile Howard Street Tunnel, six short tunnels in Northern Baltimore; a viaduct, several other overpasses, and countless cut-and-fill operations at various locations.

    Building the tunnel
    Construction of the Howard Street Tunnel began in 1891, was completed in 1895, and posed many engineering difficulties for the B&O. Howard Street was a main north-south route and was densely populated along the entire 1.4-mile route. Lining the road above were residences, retail stores, academic institutions, and other commercial establishments. Around this time, Howard Street was home to a horse car line and carried substantial wagon and carriage traffic. If that wasn't enough, the city was in the process of constructing a cable-powered street railway. The conditions under ground were not much better. The earth was mostly clay and sand and was littered with quicksand produced from several underground streams running through the area. Engineers would manage to overcome all of these obstacles and build the longest soft-earth tunnel in the nation, without disturbing anything on the surface. The Howard Street Tunnel would end up being the longest tunnel on the entire B&O system.

    To accomplish the construction of the Howard Street Tunnel and the remainder of the Belt Line, the B&O hired Pennsylvania Railroad assistant to the vice president, Samuel Rea, as the Belt Line's Chief Engineer. Although Rae resigned in late 1891, long before the project was complete, the tunnel was opened on May 1 1895. It was constructed, using over 30 million bricks, took 56 months to build, had a grade of 35 degrees, and a length of 1.7 miles. Originally it was constructed for two track operations, one in each direction, however; the tunnel was later reduced to a single track due the increased size of railcars. Tunnel depth varied from three feet at the south end to 49 feet at the north end.

    The tunnel exits trains in a northeasterly direction toward Wilmington, Del. From this end, B&O trains would run into Philadelphia via Central Railroad of New Jersey and Reading trackage. The Mount Royal Station opened in 1896 at the north end of the tunnel, and served B&O mainline passengers until April 30, 1958. Local service continued to Mount Royal until 1961, when it was permanently closed. Currently the train station houses an art gallery.

    Running in the tunnel
    Due to its length and grade, the Howard Street Tunnel was an operational nightmare. Smoke and toxic gases from the steam locomotives would have made going through the tunnel a miserable experience, at best, for locomotive crews and passengers. Prior to the tunnel's construction, B&O engineers realized they had to find an alternate to steam power for use in the Howard Street Tunnel. The Pennsylvania, faced with the same problem 20 years earlier, was forced to construct huge ventilation chimneys above the tunnel, carrying the toxic gases into the open air above the streets of Baltimore. Fortunately for the B&O, these chimneys would prove to be unnecessary. When construction of the tunnel began the motive power for trains through the tunnel was undecided but several recent events were pointing the B&O to the use of an emerging technology. In 1885, an electrified horse car line was in successful operation in Baltimore and an electrified streetcar system was in operation in Richmond, Virginia.

    The picture below shows The last northbound Royal Blue disappears into the mist at the Camden Station in Baltimore in April 1958. The Camden Station is just south of the Howard St. Tunnel. Photo from the Collection of the NRHS.

    Electrics slow to the rescue
    The problem facing the B&O was that present-day electric railroad technology was still not able to haul the heavy loads that would routinely run through the Howard Street Tunnel. By the early 1890s, electric locomotives designed for heavy rail service were thought to be a possibility, but none had yet to be produced. In 1892, in a purely speculative vain, the B&O signed a contract with General Electric to build a locomotive capable of performing in the Howard Street Tunnel.

    The plan was to operate westbound trains (those trains that were descending the grade) by allowing the steamers to "coast" downhill. Since they were not working up a heavy grade, the heavy, toxic smoke would not be produced. For trains in the eastbound direction (those trains that were ascending the grade), an electric locomotive would be attached and would pull the train through the tunnel while the steam engine just idled through the tunnel.

    By 1893, GE had produced a four-wheel, 30-ton switcher. Considering that a year earlier they hadn't produced a single electric locomotive for heavy railroad service, this is considered a remarkable achievement. Despite not being large enough to operate trains through the Howard Street Tunnel, the unit was operational, and GE committed to building a complete system for the B&O: power generating plant, locomotive capable of moving specified loads up the grade at specified speeds, and the necessary electrical distribution systems.

    Help finally arrives
    The first electric locomotive was delivered to the B&O in June of 1895 from GE's Schenectady, New York plant. Numbered 1 on the B&O roster, it was the first electric locomotive to run on an American steam railroad and entered service on June 7, 1895. It was quickly put to work on freight runs, while passenger trains through the tunnel continued to be steam powered, while the unit was being tested. The second unit arrived in November 1895, and the third arrived in May of 1896. The electric units weighted a total of 98 tons each and had four pairs of 62-inch drivers contained in a two-section articulated frame. The four electric motors provided 360 hp each and produced 49,000 pounds of tractive effort. The units were able to pull 500-ton passenger trains upgrade at 35mph and 1,500-ton freight trains upgrade at 15mph.

    Passengers "in the way"?
    As the B&O worked to solve its complicated engineering problems, it began working on plans for additional passenger stations along the Belt Line route. Initially these plans called for three new stations along the route. One was to be constructed inside the Howard Street Tunnel itself, a second was to be constructed just north of the Tunnel, and the last was to be constructed in Peabody heights, a suburb of Baltimore. In the end only one station, Mount Royal, just north of the tunnel was constructed. The other two stations were scrapped partly due to the anticipated difficulty of running significant passenger traffic through the tunnel and also due to the financial problems that were mounting for the B&O. B&O management feared that the increased passenger traffic would create a bottleneck for the movement of large freight trains through Baltimore, which is exactly the problem the tunnel was supposed to solve.

    Below: B&O Called its Budd RDCs "Speedliners." Here, Speedliner Trian No. 166 from Washinhgton has arrived att the cavernous Mt. Royal station in December 1959, after passing through Howard Street Tunnel. the north (east) portal may be seen in the background. Photo by Frank G. Tatnall

    Building the beast
    The construction of the Howard Street Tunnel was a long and difficult job. For the most part, construction proceeded with only minor problems. Frequently, daytime work on the Tunnel would cause the street pavement above to sink several feet requiring a quick rebuild during the night. The only significant incident was the destruction of a City College building, dating from 1874 that became structurally unstable due to an underground pool of water that contractors inadvertently opened. When the tunnel's construction was finally completed, a new building was built to replace the demolished one.

    Electrification ends
    The electrification of the tunnel remained until the 1940s, when diesel locomotives made it unnecessary. Currently, the tunnel is owned and operated by CSX. CSX views the Howard Street Tunnel as essential to its operation but a traffic bottleneck. Recently, CSX has taken steps to improve the situation. They dried out the bores of the tunnel and increased the speed limit from 10 mph to 25 mph. Although the tunnel has been improved greatly in recent years, it's in need of substantial work to ensure its safe operation in the future. In the meantime, the Howard Street Tunnel remains an essential route for moving freight through the city of Baltimore.

    Sources:
    1) Harwood, Herbert, H. Royal Blue Line. Sykesville: Greenberg Publications, 1990
    2) Manion, Paul. "The Howard Street Tunnel." The Sentinel. July/August 1990: 6-21.
    3) Article from Those Classic Trains published on the web at http://www.northeast.railfan.net/classic/BnOdata6.htm



Click for Information about the NRHS Service Mark